Development Finance

What Happens If Development Costs Increase?

Quick answer

Cost overruns are usually covered by

1x borrower first 0 automatic lender increase

In most cases, the developer must solve the shortfall unless the lender agrees to amend the facility

  • Typical contingency allowance 5 to 10%+
  • Common funding response Extra equity
  • Key independent review QS cost to complete
icon 1300 421 044 1300 421 044

If development costs rise after a loan is approved, the lender does not automatically increase the facility. In many cases, the borrower is expected to cover the shortfall first through cash, extra equity, or another approved source of capital.

Before further funding is released, the lender will usually reassess the revised budget, contingency, cost to complete, expected end value, and whether the project still has a credible exit.

If the increase is significant, the solution may involve extra equity, a joint venture injection, a facility variation, or refinance to a more flexible lender. A quantity surveyor report often becomes central to that decision.

What usually causes development cost overruns?

Cost overruns can occur on small and large developments. They are not limited to apartment towers. Townhouses, land subdivisions, mixed use sites, and commercial builds can all run over budget if assumptions prove too optimistic.

Lenders usually look closely at the cause of the overrun because there is a big difference between a manageable variation and a project that was under costed from the beginning.

Common causes include:

  • iconBuilder price increases or labour and material escalation
  • iconLatent site conditions such as rock, drainage, or service upgrades
  • iconDesign changes and authority required variations
  • iconProject delays increasing interest, preliminaries, and holding costs
  • iconOriginal contingency allowance proving too small
  • iconConsultant, civil, compliance, or selling costs rising above budget

What lenders do when costs increase

A lender will usually pause and reassess rather than simply keep funding under the original assumptions.

That review focuses on the revised budget, remaining contingency, updated timing, and whether the project still has a workable debt and exit position.

A typical review sequence may include:

  • 01 Cost increase is identified
  • 02 QS updates cost to complete
  • 03 Lender reviews revised feasibility
  • 04 Borrower injects extra capital if required
  • 05 Facility is amended or refinanced
  • 06 Funding resumes to completion

If the project no longer meets the lender's risk criteria, further drawdowns may be restricted until the funding gap is resolved.

Who usually pays for the overrun?

When development costs increase, extra funding usually comes from one of these channels:

Source 01

Developer equity

Most lenders first expect the borrower or guarantor group to inject more cash or accessible equity if the approved facility is no longer enough.

Source 02

Facility variation or refinance

If the revised feasibility still works, a lender may consider a facility increase, restructure, or refinance to another funder with a broader risk appetite.

Common contingency range 5 to 10%+
  • Contingency is built into the original budget where possible
  • Once contingency is exhausted, extra equity is often needed

Well prepared development feasibilities normally include contingency, but contingency is not unlimited. If the actual cost to complete rises beyond the approved budget, the lender will review the remaining buffer and may require the borrower to bridge the gap before more funds are released.

What gets reassessed after a cost overrun?

Once a project goes over budget, the original feasibility is no longer enough on its own.

The lender, quantity surveyor, and sometimes the valuer may revisit the numbers to decide whether the project still works.

That reassessment commonly includes:

  • iconUpdated builder contract or revised trade budget
  • iconQS report on remaining cost to complete
  • iconRevised total development cost and contingency balance
  • iconUpdated holding, interest, and delay costs
  • iconFresh sales evidence or valuation if the market changed
  • iconRevised LVR, LTDC, and end debt position
  • iconStatus of pre sales, leasing, or refinance exit
  • iconDeveloper capacity to inject more funds
5 - 10 %
Many development budgets include contingency of around 5 percent to 10 percent or more depending on the type and stage of the project. If the overrun is bigger than the contingency, extra capital is often required.

How cost overruns can affect the loan

An overrun does not always kill a project, but it can change the funding structure very quickly.

icon

More equity may be needed

If the approved facility cap is reached, the developer may need to inject more funds before the next drawdown will be released.

icon

Timing can blow out

Re quoting, QS review, new approvals, or lender credit reassessment can delay the project and increase interest and holding costs further.

icon

Refinance may be required

If the current lender will not vary the loan, a specialist construction or private lender may be approached to refinance the revised position.

Common problems

When costs increase, problems tend to stack together. The issue is often not just the builder invoice. It is the knock on effect across debt, timing, and profit.

icon

Contingency runs out

Once the contingency allowance is fully used, the borrower has little room left inside the approved budget.

Possible solutions include:
  • icon Injecting cash from outside the project
  • icon Using equity in another property
  • icon Bringing in an equity partner
icon

Project profit shrinks

Even if the build can still finish, overruns can reduce profit enough to make the lender uncomfortable with the revised risk.

Responses may include:
  • icon Repricing the end values where justified by evidence
  • icon Cutting non essential scope or finishes
  • icon Refinancing to a lender with different parameters
icon

Completion is delayed

Time overruns usually create their own cost overruns through extra interest, preliminaries, consultant fees, and holding costs.

Borrowers often need:
  • icon An extended loan term
  • icon A revised QS cash flow forecast
  • icon More working capital for carry costs
icon

Existing lender says no

Some lenders will not top up a construction facility even if the project is still fundamentally sound.

Alternative paths may include:
  • icon Mid project refinance
  • icon Mezzanine or private capital
  • icon Additional security support

Steps To Manage A Development Cost Overrun

Step

01

Identify the overrun early and confirm whether it is one off or systemic

Step

02

Get an updated builder budget and QS cost to complete report

Step

03

Rework the feasibility including extra interest, contingency, and exit values

Step

04

Show the lender how the shortfall will be covered and when funds are available

Step

05

Request a facility variation or test refinance options with specialist lenders

Step

06

Secure the revised funding plan and keep construction moving to completion

Helpful Property Finance Guide

Copyright ©2026 Property Finance Help - All rights reserved.

Disclaimer: Property Funding Help is a lead generation service and not a lender, broker, or financial advisor. We do not provide loans or credit decisions. We connect users with third-party finance professionals who may assist with their enquiry. All information on this website is general in nature and does not take into account your personal objectives, financial situation, or needs. Before making any financial decisions, you should consider seeking independent professional advice. By submitting your details, you consent to being contacted by third-party providers.